Work done:

– masonry of the main and interroom walls of the 2nd floor was completed (on the fact of the 3rd floor)
– installation of floor slabs of the 2nd floor was made (on the fact of the third)
– installation of a flight of stairs and a platform on the 3rd floor was made)
– installation of window and door lintels on the 2nd floor was completed
– heating equipment systems are 80% complete
– the foundation is 100% ready
– ground floor for commercial premises is 100% ready
– the waterproofing and the belt between the basement and the residential floor are 100% complete
– Works on the installation of monolithic sections of the basement floor over 100% completed
– Works on laying the main walls of the first residential floor (in fact of the second) are 100% complete.
– work on the installation of jumpers door and window openings of the first residential floor (in fact the second) is 100% completed
– Works on laying the slabs of the first residential floor (in fact of the second) are 100% completed.
– installation of staircases from the first to the second residential floor;
– we make the laying of the capital walls of the second residential floor (in fact the third) by 50%

Want to be the first to know all the latest news? Greenwood LCDs in social networks:

https://www.facebook.com/greenwoodkiev/
https://www.instagram.com/greenwood.kiev/
Are there any questions? Our managers are ready to help you choose an apartment.
We work:
Mon-Sat: 10:00 – 19:00
Sun: Weekend
Details: +38 (068) 427 23 42