Work done: – masonry of the main and interroom walls of the 2nd floor was completed (on the fact of the 3rd floor) – installation of floor slabs of the 2nd floor was made (on the fact of the third) – installation of a flight of stairs and a platform...
Course of construction 27.09.2018

Course of construction 27.09.2018

Performed works: – heating systems are 80% – the foundation is ready for 100% – ground floor for commercial premises is ready for 100% – waterproofing and the belt between the socle and the living floor are 100% – work has been completed...
Course of construction 10.09.2018

Course of construction 10.09.2018

Completed work: – work has been completed on the construction of monolithic sections of the basement floor; – work has been completed on the installation of the masonry of the first residential floor (after the second); – Works on installation of...
Course of construction 17.08.2018

Course of construction 17.08.2018

Work done: – completed work on the installation of monolithic areas of overlap of the ground floor; – We are approaching the completion of the masonry unit of the main walls of the first living floor (on the fact of the second one); – parallel work...
Course of construction 01.08.2018

Course of construction 01.08.2018

Work done: – from the laying of ceiling slabs of the ground floor; – work on the laying of laying of the main walls of the first floor has begun; Want to be the first to know all the latest news? Greenwood LCDs in social networks:...
Course of construction 19.07.2018

Course of construction 19.07.2018

Completed work: for waterproofing and warming the foundation and the basement floor backfilling with ground basement masonry device for monolithic belt reinforcement of a monolithic belt installation of formwork on a monolithic belt concreting monolithic belt on the...