Completed work:

– work has been completed on the construction of monolithic sections of the basement floor;
– work has been completed on the installation of the masonry of the first residential floor (after the second);
– Works on installation of jumpers of door and window apertures of the first residential floor (after the second) have been completed;
-work was done on laying the slabs of the first residential floor (after the second)
-work began on the construction of the masonry walls of the second residential floor (after the third);
– installation of stair flights from the first to the second residential floor;