Performed works:

– heating systems are 80%
– the foundation is ready for 100%
– ground floor for commercial premises is ready for 100%
– waterproofing and the belt between the socle and the living floor are 100%
– work has been completed on the construction of monolithic sections of the basement floor covering by 100%
– work has been completed on the installation of the masonry walls of the first residential floor (after the second) by 100%
– work has been completed on the installation of jumpers for door and window openings of the first residential floor (after the second) by 100%
– work was carried out on laying the slabs of the first residential floor (in fact, the second) by 100%
– installation of stair flights from the first to the second residential floor;
– We make the device of laying the capital walls of the second residential floor (after the third) by 50%

Want to keep up to date with all the latest news? Greenwood in social networks:

  • https://www.facebook.com/greenwoodkiev/
  • https://www.instagram.com/greenwood.kiev/

Have questions left? Our managers are ready to help you in choosing an apartment.
We work:
Mon-Sat: 10:00 — 19:00
Sun: Weekend
More info:+38 (068) 427 23 42