Completed work:

– The main and interroom walls of the 3rd residential floor are being laid (in fact, 4 floors). Laying of 3 floors is 60% complete.
– masonry of the main and interroom walls of the 2nd residential floor was completed (in fact, 3 floors)
– installation of floor slabs 2 residential floors (on the fact of the third)
– installation of a flight of stairs and a platform on the 3rd residential floor
– installation of window and door lintels on the 2nd residential floor was completed
– heating equipment systems are 80% complete
– the foundation is 100% ready
– ground floor for commercial premises is 100% ready
– the waterproofing and the belt between the basement and the residential floor are 100% complete
– Works on the installation of monolithic sections of the basement floor over 100% completed
– Works on laying the main walls of the first residential floor (in fact of the second) are 100% complete.
– work on the installation of jumpers door and window openings of the first residential floor (in fact the second) is 100% completed
– Works on laying the slabs of the first residential floor (in fact of the second) are 100% completed.
– installation of staircases from the first to the second residential floor;
– we make the laying of the capital walls of the second residential floor (in fact the third) by 50%
Want to be the first to keep up with all the latest news? LCD Greenwood in social networks:

• https://www.facebook.com/greenwoodkiev/
• https://www.instagram.com/greenwood.kiev/
Any questions? Our managers are ready to help you and help you choose an apartment.