Course of construction 31.10.2018

Course of construction 31.10.2018

Completed work: – The main and interroom walls of the 3rd residential floor are being laid (in fact, 4 floors). Laying of 3 floors is 60% complete. – masonry of the main and interroom walls of the 2nd residential floor was completed (in fact, 3 floors)...

Work done: – masonry of the main and interroom walls of the 2nd floor was completed (on the fact of the 3rd floor) – installation of floor slabs of the 2nd floor was made (on the fact of the third) – installation of a flight of stairs and a platform...
Specifications of Greenwood

Specifications of Greenwood

We decided to slightly open the curtain and tell about the important technical characteristics of the LCD GREENWOOD: Floors and area: – for the project a modern, energy-efficient club house has 5 floors, of which the total area of ​​the apartments is –...
Course of construction 27.09.2018

Course of construction 27.09.2018

Performed works: – heating systems are 80% – the foundation is ready for 100% – ground floor for commercial premises is ready for 100% – waterproofing and the belt between the socle and the living floor are 100% – work has been completed...
Course of construction 10.09.2018

Course of construction 10.09.2018

Completed work: – work has been completed on the construction of monolithic sections of the basement floor; – work has been completed on the installation of the masonry of the first residential floor (after the second); – Works on installation of...