External works:
– façade works performed by 95%;
– complete installation of the roof ;.
– installation of windows on residential and commercial floors is 100% complete
– installation of the entrance group of the house;
– work started on the adjoining territory.
Internal works:
– completed laying of interior walls on all residential floors;
– completed installation of the heating and water supply system;
– sewer installation is 100% complete
– installation of power grids in public places;
– Schindler lift equipment installed;
– Electricity generation in flats with installation of shields is completed;
– installation of the heating system in apartments with installation of radiators of the Purmo company is performed by 90%;
– preparation of the floor screed in apartments;
– Prepare public areas for plaster and screed
– The preparatory work of the plastering of the walls on the stairs is being carried out

Want to be the first to know all the latest news? Greenwood LCDs in social networks:

https://www.facebook.com/greenwoodkiev/
https://www.instagram.com/greenwood.kiev/
Are there any questions? Call our sales team and our managers will help you find the apartment of your dreams.

Kyiv, Kislovodskaya Str. 100

Phone: 

+38 068 427 23 42

+38 066 007 43 93

The schedule of the sales department:

Mo-Fr 10:00 – 19:00
Sa 11:00 – 18:00
Sunday – 11:00 – 17:00

Email:

info@greenwood-kiev.com

Course of construction 18.01.2020
Course of construction 18.01.2020
Course of construction 18.01.2020
Course of construction 18.01.2020
Course of construction 18.01.2020
Course of construction 18.01.2020
Course of construction 18.01.2020
Course of construction 18.01.2020
Course of construction 18.01.2020
Course of construction 18.01.2020
Course of construction 18.01.2020
Course of construction 18.01.2020
Course of construction 18.01.2020